A
new master plan for Dawei Special Economic Zone (SEZ) near Dawei in the
Taninthayi Region was adopted with the assistance of the Japan International
Cooperation Agency (JICA) after the project was adjourned for various reasons.
Here is an interview with Vice-Chairman Dr Myint Hsan of Management Committee
of Dawei SEZ.
Q:
When will Myanmar launch Dawei SEZ?
A:
In 2008, the Myanmar and Thai governments met in Singapore and conceived a plan
to implement the Dawei SEZ project. The two then signed a Memorandum of
Understanding (MoU). At first, the Myanmar Port Authority signed an agreement
with an Italian-Thai company. Because of the delay, the agreement was
terminated in 2013. The tenders were invited again.
The
same company won the tender. A new agreement was reached in 2015 between the
management committee and the Italian-Thai company, and the works were resumed.
The project was stopped between 2013 and 2014. The Myanmar and Thai governments
then signed an agreement to implement the project themselves. However, the
investment from Thailand was small.
As
it was impossible for the Italian-Thai company alone to implement the project,
a new agreement was signed by Myanmar, Thailand and Japan.
Q:
What are the functions of the Management Committee of Dawei SEZ?
A:
We started our work in October 2017. We have to look into the details of the
agreement reached with the Italian-Thai company and also the three-country
agreement. We found 78 points that need bilateral implementation —58 points for
Thailand and 20 points for Myanmar. We can resume work only if these points are
fulfilled.
The
Myanmar government did its best to fulfil the requirements. Currently, only one
or two remain. They are important matters such as EIA (Environmental Impact
Assessment) and SIA (Social Impact Assessment). They are a bit complicated and
difficult. However, now the EIA and SIA are nearly completed. A law firm will
be hired for land agreements. We asked the Italian-Thai company to implement
its part. We will begin the project soon after the two aides fulfil their
agreements. The work will start according to the portion-wise time schedule.
Another
part in the portion is called full phase. We have requested the Japanese government
to take charge of that phase. A master plan was drawn by Thailand in 2015, but
it had no detailed facts and was outdated. So JICA tried to upgrade the master
plan.
The
Japanese said that a new plan must be drawn and that it must include the
technical details. They drew a new master plan in 2017 and completed it in
2018.
It
has three phases. Phase-1 will be implemented between 2018 and 2030, but the
area lacks infrastructure. We need at least a two-lane highway. No electricity
and jetties exist. Without infrastructure, foreign investment is not possible.
So we are giving priority to it.
Some
6,000 acres of land were fixed for phase-1. We will build the infrastructure
during the 2018 to 2030 period. Foreign investment may come in only after three
years.
JICA
will finalise its plan in May. Phase-1 will deal with the infrastructure,
investment by the Myanmar government, foreign loans and a deep-sea port.
Currently, only Dawei and Kyaukphyu have a deep-sea port project.
Q:
What are your plans to supply enough power?
A:
The Italian-Thai company has an LNG project for power supply. So we will need
large LNG tanks. We urged them to build the facilities, but they couldn’t. Plan
B was to import LNG. But the rate they proposed was too high. The price in the
neighbouring country is usually only 10 cents, but their rate is 27 cents now.
The
Ministry of Electricity and Energy has already signed with Total to generate
more than 1,300 megawatts of LNG in Kanbauk. Power will be
available within three years. The whole Taninthayi Region will be electrified
in 2021.
Q:
Could you tell us about the plans for the Thiki road that connects Dawei SEZ
with Thailand.
A:
The Italian-Thai company will construct the 138-kilometre road as a gravel
road. The Thiki road is crucial, and the previous government’s administration
planned to upgrade it to a tar road, but it was never accomplished due to
certain reasons. We don’t have sufficient funding to construct a road, so we
will acquire a loan from a Thai group called NEDA. But we need the approval of
the Hluttaw first, and if they approve the loan, then we will contact the Thai
group and call for a tender for the project, which we estimate will take three
years.
Q:
How will Dawei develop after the SEZ is established?
A:
It is pretty significant. The SEZ is a deep-sea port and is close to Thailand,
so potential development opportunities exist.
The
Taninthayi Region is abundant in natural resources, fishery businesses, rubber
plantations, oil palm and mineral productions. But it does not have the
electricity to produce high-end finished products yet.
Once the SEZ is completed, we will be able to produce high-quality products
that can rival our neighbours. This will in turn boost the economy and create
jobs.
Q:
Local residents have voiced fears about the SEZ damaging the natural
environment. What measures are being taken to prevent this?
A:
In the past, no EIA or SIA were conducted when projects were carried out, and
it was obvious the natural environment was being damaged. But now, the
democratic government has ensured projects are more transparent, with the
vision to reduce as much harm to the environment and to the society as
possible.
Now,
you cannot start a private company without providing an EIA or SIA. All the
projects related to the SEZ have submitted their EIA and SIA to the union
government, and we had a meeting with the local people to inform them of these
practices and to answer all their questions and concerns.
Q:
Are there other plans to ensure the SEZ’s plans and environmental reports are
more transparent?
A:
We know it is obligatory to put up our environmental reports online but, for
some reason, we are still unable to launch our website. I
have been told it will be up and running in two weeks. All the EIA and SIA
reports will be available online, and people can submit questions on the
website. The democratic government will not maintain any secrecy.
Q:
What are your projections for investment prospects once the SEZ is completed?
A:
It will take three to five years to complete the construction of roads, basic
infrastructure and to supply electricity to the area.
Once
these are completed, more investments can be expected, but large industrial
works will be minimal initially. We will also need to upgrade and develop the
rubber factories and fishery-related factories in our region.
Japanese
companies, such as those with a firm foothold in Thailand, are interested in
the steel industry and the automotive industry. Being a least developed country
(LDC), Myanmar has numerous trading opportunities. For example, Thailand does
not receive a GSP (Generalised Scheme of Preferences) and needs to pay tax to
export to the EU and the United States, but Myanmar has a GSP and enjoys free
trade. We have received these opportunities but have yet to make use of them.
Q:
What is the most difficult challenge the project is facing currently?
A:
The most pressing concern right now is that of the project developer.
Currently, the Italian-Thai company is leading the project, but it has
financial difficulties, and so cannot achieve optimal performance. But we must
employ a financially stable and internationally experienced developer during
the full phase of the project. After we complete the master plan in May, we
will employ developers for each project.
Q:
Do you have any closing remarks?
A:
Leading a project requires political stability, national integrity, active
participation and support from one’s government for the project to take off and
succeed. These are national-level projects and thus require in-depth
participation from the union government.
Interviewers:
Thi Thi Min, Min Thit (MNA)
PHOTO:
NAY LIN
Ref;
The Global New Light of Myanmar
No comments:
Post a Comment