The Republic of the Union of
Myanmar
The Union Government Office
Notification
Order No. 66/2015
6th Waning of
First Waso, 1376 M.E
(7 July 2015)
Termination
of the Project
1. With the aim of contributing the city
development work to the building of Yangon into a modern city, the Ministry of
Defence invited tender for enabling to carry out development works of the old
site of the former National Defence College and No.1 Motor Transport Battalion
that are no longer in plan to use and the following companies won the tender:
(a)
Shwe Taung Development Co., Ltd.
(b)
Adventure Myanmar Tours and Incentive Co., Ltd.
(c)
Thukha Yadana Co., Ltd.
(d)
Marga Landmark Development Co., Ltd.
2. The aforesaid tender-winning companies submitted
their requested plans including hotels of international standard, service
apartments, department stores, business centres, residential buildings to the
Myanmar Investment Commission. The Myanmar Investment Commission scrutinized
and issued permits to the companies in accord with the Foreign Investment Law
and Myanmar Citizens Investment law.
3. While the development project is being
implemented, some people have become concerned that the project may harm the
Shwedagon Pagoda, some scholars forwarded their assessments over the project to
the President, some people who are concerned over the project implementation
made the request to terminate the project to the President, the Myanmar Investment
Commission submitted assessment that the project is not appropriate for further
implementation, the Ministry of Defence also asked the project to be
terminated, the Government is desirous of carrying out in priority to what do
not harm temples and pagodas, religious edifices and ancient cultural heritages
on Theinguttara Hill including the Shwedagon Pagoad and the investors willingly
agreed over the termination of the project after negotiating; all the on-going
projects have been conclusively terminated commencing from the date of issue of
this notification.
4. The government will take further necessary
measures in order not to affect and aggrieve the investors who are investing
and carrying out in the project due to the conclusive termination of the
project.
By
order,
(Zaw
Than Thin)
Secretary