Shwe Kokko Phase II demolition continues

 



TREATING the fight against telecom fraud and online gambling as a matter of national duty, the Government is systematically demolishing illegal structures in the Shwe Kokko area to prevent them from being reused for scam and gambling operations.

As part of operations targeting the remaining illegal buildings in Shwe Kokko Phase II, heavy machinery has been deployed to dismantle key structures. Demolition of a five-storey building is 75 per cent complete, while work on a six-storey building is 20 per cent complete.

Of the 63 buildings designated for demolition in Phase II of the Shwe Kokko area, ten have been demolished, including four through controlled explosions and six using heavy machinery. The remaining 53 buildings will also be systematically demolished.

100/MKKS

#TheGlobalNewLightOfMyanmar